In 2009, the Municipality of Aaron-Elderslie, required a safe, cost effective method to clean one of its 3 lagoon cells. Four Geotube® units measuring 30’ x 100’ were used with the addition of a polymer injection systems and dredge. Geotube® sludge removal saved money, time and delivered a cleaner option than previous clean outs.